Chillicothe News - Chillicothe, MO
  • Street milling begins Thursday

    • email print
  • According to M & M Utilities, their subcontractor, APEC, will be in Chillicothe on Thursday and Friday, weather permitting.
    They will be milling some streets but not all. All the streets listed will be receiving an asphalt overlay of between one inch and two inch. This is the order they have planned:
    Thursday — Borden, from Lambert to Dorney; and Country Club Drive, from Fairway to Dorney
    Friday — Jackson, from Dickinson to Highland; 10th, from Broadway to 11th; 10th, from Trenton to Oak; and Webster, from Elm to Vine.
    While this construction work is taking place, all residents must have their cars parked off the street for the day.