  • Work continues at the new Route V Bridge construction site.
    • email print
  • Work continues at the new Route V Bridge construction site. Michael Marriott, Int. Construction Inspector for the Missouri Department of Transportation’s Northwest District, said he hopes to finish tying steel rebar for the bridge deck today (Wednesday). Concrete should be poured tomorrow or Friday, depending on weather. Asphalt should be laid by the end of next week. Marriott said the plan is to have the bridge open by Thanksgiving or early December.