Construction on the new elementary school continues to move along toward the May 2018 scheduled completion.

Construction on the new elementary school continues to move along toward the May 2018 scheduled completion. Roof construction will begin this week and is expected to take two to three weeks. Next week, crews will start paving roads through the campus and that project is expected to take two or three days to complete. The overall project has fallen behind by a few weeks, but better than usual winter weather allowed construction crews to get ahead back then. Project manager, Eric Link, said “We’re still making good time.” This photograph was taken via a drone and provided by Tim Marsh.